Optimal MRP offsetting for assembly systems with stochastic lead times: POQ policy and service level constraint

Mohamed-Aly Louly 1 Alexandre Dolgui 2 Abdulrahman Al-Ahmari 1
2 Laboratoire en Sciences et Technologies de l'Information
DEMO-ENSMSE - Département Décision en Entreprise : Modélisation, Optimisation
Abstract : This study deals with component supply planning in assembly systems, i.e. where several types of components are needed to produce one finished product. The actual component lead times have random deviations, so they can be considered as random variables. MRP approach with Periodic Order Quantity policy is considered. The aim is to find the optimal MRP offsetting. The proposed model and algorithms minimize the sum of the setup and average holding costs for the components, while satisfying a desired service level.
Document type :
Journal articles
Complete list of metadatas

https://hal-emse.ccsd.cnrs.fr/emse-00673896
Contributor : Florent Breuil <>
Submitted on : Friday, February 24, 2012 - 2:50:34 PM
Last modification on : Thursday, October 17, 2019 - 12:36:46 PM

Links full text

Identifiers

Citation

Mohamed-Aly Louly, Alexandre Dolgui, Abdulrahman Al-Ahmari. Optimal MRP offsetting for assembly systems with stochastic lead times: POQ policy and service level constraint. Journal of Intelligent Manufacturing, Springer Verlag (Germany), 2012, Volume 23 (Issue 6), pp 2485-2495. ⟨10.1007/s10845-011-0515-7⟩. ⟨emse-00673896⟩

Share

Metrics

Record views

192